Clear, timely and comparable network connection cost information helps renewable energy and storage developers plan, compare and optimise their projects.

As connection volumes grow, there is an opportunity to improve the transparency, predictability and efficiency of network connection costs and the commercial processes that surround them.

The Network Costs workstream of the Connections Reform Initiative will bring together transmission network service providers (TNSPs) and project developers to identify practical improvements that can be adopted across the National Electricity Market (NEM).

Stakeholder engagement is taking place now to help deliver recommendations in the first half of 2027.

The Network Costs workstream seeks to improve the transparency, predictability and efficiency of network connection costs and associated commercial processes for TNSPs and developers.

Stage 1 will identify best practice that can be adopted under the current rules and co-design draft templates for more granular and timely cost and schedule information. The workstream will also assess whether an independent, anonymised review of network connection costs or a targeted rule change should be progressed.

Templates will focus on transparency and comparability. They will not prescribe prices or interfere with competitive procurement, and discussions will not cover project-specific prices, bids, margins or future commercial strategies.

Projects count on reliable cost information, but getting accurate network costs can be challenging for several reasons, including:

• Network connection cost information is sometimes high-level, inconsistently presented or provided relatively late in the connection application process, making costs difficult for developers to compare, plan for or optimise.

• Bespoke equipment specifications and non-standard requirements can add cost and time that may be avoidable in instances where viable alternatives exist.

• Contestable and non-contestable works procurement, design approval timing and connection-offer validity periods are not always consistently sequenced, creating delays and rework.

• Designated Network Asset (DNA) access policy negotiations can be time-consuming, and funding and cost recovery for additional capacity for future users are not always clear.

These issues create commercial friction and reduce predictability, yet no structured, NEM-wide process currently exists to resolve them within appropriate competition-law boundaries.


Stage 1 aims to build a shared, evidence-based understanding of network connection cost issues and identify practical improvements.

Stage 2 would implement some or all of the improvements identified in Stage 1. It seeks to deliver benefits for three groups:

• Developers: more transparent, comparable and timely cost information, and reduced risk of late-stage cost surprises and project delays or rework.

• TNSPs: clearer, more consistent practices for presenting cost and schedule information, reduced disputation and rework, and an overall reduction in workload from a more efficient process.

• The NEM: more efficient and predictable connection processes that support timely investment, while maintaining appropriate competitive and commercial boundaries between participants.

Stage 1: Review and recommend

In Stage 1, an independent facilitator will run competition-law-compliant roundtables with TNSPs and developers. This stage will include:

• Conducting a research and literature review including information on current cost and process practices and cost and schedule information templates used across various jurisdictions. 

• Using stakeholder-led design to shape improvements through testing pain points and co-designing draft cost and schedule templates.

• Developing a clear reform pathway.

• Producing a final report with recommendations and supporting templates for agreed improvements.

Stage 2: Implement recommendations

Stage 2 would implement some or all of the recommendations. Any independent cost review, rule change or material implementation program will require separate scoping, funding and approval.

Building better connections together

The success of the CRI to date has only been possible due to the contributions of industry participants who have volunteered their time, expertise and resources to support reform development and implementation. 

AEMO and the Clean Energy Council acknowledge and thank the organisations and individuals who have contributed to the initiative and continue to support Phase 2 activities.

To enquire about participating in the CRI, contact connectionsreform@cleanenergycouncil.org.au or contact.connections@aemo.com.au.