Planning, biodiversity and coordination reform options to facilitate renewable energy projects in NSW 

Recommendations to accelerate clean energy in the state

Share the report
<p>Planning, biodiversity and coordination reform options to facilitate renewable energy projects in NSW&nbsp;</p>

The reforms needed to unblock renewable projects in NSW

The CEC and its members are deeply invested in the ongoing success and reliability of the NSW electricity sector and are excited to help realise the significant opportunities that renewable energy presents for the State, communities and industry. These opportunities are clearly reflected in the NSW Electricity Infrastructure Roadmap, which is expected to attract up to $32 billion in private investment in renewable energy infrastructure to 2030, and support an estimated 6,300 construction jobs and 2,800 ongoing jobs, mostly in regional NSW, in 2030.

NSW's energy sector is at a critical delivery stage. With coal-fired power stations retiring on fixed timelines, the decisions made in the next few years on planning and biodiversity assessments for renewable energy projects will determine whether the state can replace that capacity in time and capitalise on this significant investment opportunity.

Our policy paper, Planning, Biodiversity and Coordination Reform Options to Facilitate Renewable Energy Projects in NSW, sets out 29 practical recommendations to help unlock the pipeline of renewable energy projects currently awaiting approval.

The paper was prepared with strategic and technical insights from Umwelt, a leading Australian environmental and social consulting firm and Clean Energy Council member.

The paper presents a range of practical reform opportunities the NSW Government could support to help deliver the State’s energy transition.

Biodiversity assessment reforms
The current biodiversity assessment framework for renewable energy projects in NSW faces challenges associated with: evolving and often inconsistent requirements that create significant uncertainty, delay, and increased costs for proponents. Key issues include ongoing ‘requirement creep’ during assessment, improving the effectiveness of strategic offset delivery agreements and standardising the approach for partial and temporal impacts.
Planning approval reforms
As the scale and extent of the NSW renewable energy sector has grown over recent years, there has been an associated increase in the level of public interest, longer planning assessment timeframes, and more complex and costly technical studies and EIS processes. Extended, multi-year assessment processes can incentivise proponents to commence technical studies based on conservative footprints and early design assumptions, with refinements then occurring in parallel with impact assessment. The recommendations include clearer pathways for projects in Renewable Energy Zones, reduced planning fees and the introduction of a renewable energy State Environmental Planning Policy (SEPP).
Enabling infrastructure and coordination reforms
Shared infrastructure challenges, from road upgrades to waste management, are being assessed project by project rather than addressed strategically. The paper recommends a statewide road network assessment, regional laydown facilities, and clearer policy guidance on decommissioning obligations and bonding arrangements.

“These proposals are about aligning the regulatory system with the scale, pace and complexity of what is being asked of the renewable energy sector.”

Planning, biodiversity and coordination reform options to facilitate renewable energy projects in NSW